Loading…
(888) 704-6588
1312 Akron Drive, Nekoosa, WI 54457

Building

Index Forums General Information Building

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #3218
    Dan Horkan
    Participant

    I haven’t seen anything listed about the building project that was to be underway in Dec.
    Just wondering what’s taking place with it.
    Is it being enclosed already. I heard that they couldn’t pour concrete this winter and didn’t understand that if the building is up we pour all winter.
    After everyone was so excited about this I can’t believe there’s nothing said about it.

    #3219
    Tate Barwald
    Moderator

    Building update is in the last minutes

    #3220
    Dan Horkan
    Participant

    Thanks Tate
    I was thinking something would’ve happed in the last month even if concrete was not poured

    #3227
    Al Mccord
    Participant

    Are they still working on it? Last we saw was posts were in the ground! Hope the cold weather didn’t stop all work.

    #3231
    Dick Otto
    Participant

    The contractor for the building would like to get started, as quickly as the weather permits. They will be doing the building exterior and leave openings for the pouring of the concrete when the frost gets out of the ground. I suspect that the building will be enclosed by the time weather permits the pouring of concrete. There is a BOD meeting in the Rapids this Saturday. I suspect that Chops will present an updated building progress plan at that meeting.

Viewing 5 posts - 1 through 5 (of 5 total)
  • You must be logged in to reply to this topic.